近日,惠生清洁能源科技集团股份有限公司(以下简称“惠生清洁能源”)总承包的NGUYA FLNG项目在刚果(布)黑角海域举行首船LNG发运仪式。该里程碑标志着装置全工艺流程成功贯通并投入运行,为后续实现长期安全、稳定、高效运行及LNG外输奠定坚实基础;同时,也为惠生EPCIC一体化交付体系的成熟度与可靠性提供国际层面的有力背书。
首船LNG发运的实现,是对NGUYA FLNG总体工艺路线、工程设计完整性与关键设备性能的系统性验证,意味着核心液化工艺技术及其全装置的控制逻辑经受了实气工况检验、关键设备在设计工况下实现稳定运行,充分体现惠生在复杂系统集成与投产组织方面的能力。该节点的顺利达成,也进一步夯实了公司在全球FLNG市场的综合实力与竞争优势。
NGUYA FLNG项目为意大利Eni集团授予惠生清洁能源的EPCIC(设计、采购、建造、安装和调试)总承包合同。继创造“合同签署至开车仅35个月”的纪录后,NGUYA FLNG 又在黑角海域实现首船LNG发运。连续关键节点高效兑现,充分体现了惠生EPCIC一站式交付模式在大型浮式能源项目上的高效统筹与执行优势。
值得一提的是,近期惠生清洁能源与Eni签署NGUYA FLNG运维服务合同,推动双方合作由工程交付和开车投产向运营维护的自然延伸,也标志着惠生浮式生产业务全生命周期服务能力体系的重要升级。
未来,惠生清洁能源将继续以安全、质量与交付为核心,协同各方推进浮式能源装置稳定运行与产能爬坡,为全球伙伴创造长期可靠价值,并以持续可复制的工程能力与全周期服务能力,助力全球海上油气资源高效开发与能源供给体系的韧性提升。
NGUYA FLNG Achieves First LNG Cargo, Enters a Critical Trial Production Phase
The Launch Ceremony of the First NGUYA FLNG Cargo Loading was recently held for Eni’s NGUYA FLNG offshore Pointe-Noire, Republic of the Congo, which is being executed by Wison New Energies as the EPCIC contractor. The achievement confirms the successful completion of key commissioning and start-up activities, with the full process train lined up and the project entering the operation phase, laying a solid foundation for long-term safe, stable and efficient performance and LNG export. It also provides strong international endorsement for the maturity and reliability of Wison New Energies’ integrated EPCIC delivery system.
First LNG Cargo provides a comprehensive validation of the overall process scheme, engineering integrity and the performance of critical equipment. The core liquefaction technology package and its ICSS system have been proven under live gas conditions, with key equipment operating steadily within the design envelope — demonstrating Wison's capabilities in complex system integration and commissioning/start-up execution management.
Following the “35 months from the contract award to start-up” record, NGUYA FLNG achieved first cargo offshore Pointe-Noire — highlighting the efficiency of Eni’s fast track development model and end-to-end strength of Wison’s one-stop EPCIC capability for large-scale floating energy projects.
Notably, Wison New Energies and Eni have recently signed an Operations and Global Maintenance Services (O&M) contract for the NGUYA FLNG, extending the collaboration beyond project delivery and start-up into the operations and maintenance phase, and further strengthening Wison’s full-lifecycle service portfolio and capability.
Looking ahead, Wison New Energies will remain committed to safety, quality and delivery excellence, partnering with stakeholders to support stable operations and ramp-up, and create long-term value for global partners.